June 19, 2002 Contractors say schools will be ready for opening day By Angela Boudreaux The Ascension Citizen The flooring may not all be installed, the wiring isn't quite ready and there are plenty of walls left to be painted, but contractors working on the new Dutchtown High School are insisting the work will be complete by their July 14 deadline - less than a month from now. Just a short distance away, workers at Duplessis Primary also under construction say they'll be ready too, but there are skeptics around who say they'll have to see it to believe it. Assistant Superintendent Donald Songy said Friday that school system administrators are confident that the new high school will be ready for teachers to begin getting their classrooms ready well before the Aug. 12 first day of school. The schedule for Duplessis, though, "might be a little bit tighter," he said. "There may be a couple of sections (at Duplessis) that might not be completed by the first day of school," Songy said. "We'll use the library or conference rooms or something. We're very resourceful when it comes to things like that." Songy said if the school isn't totally complete, it would likely only be a few classrooms that would be unfinished. He said he expects the new K-5 school to be fully functioning and running smoothly within a few weeks of the school's startup. "Most if not all of Duplessis will be available to us by the beginning of school," Songy said. Parents of some students going to Duplessis Primary have been concerned the school won't be finished in time and are confused by rumors circulating about the new school. Lisa Ledet, the mother of two students who will attend Duplessis, said she heard that Duplessis students would actually be starting the new year back at the Dutchtown campus until the new facility is ready. She said she's a little surprised to hear that the school is on course to open Aug. 12 "It doesn't look like it'll be ready in time," Ledet said. Songy said all indicators point to the school being ready on time, and school system administrators will meet July 2 with the general contractor working on Duplessis to get a final update on progress there. "We'll know exactly where we stand by then," Songy said. "We'll have good, solid information to pass along to the public when we get to that point." Tommy Colomb, the general contractor superintendent whose company, Woodrow Wilson Construction, is in charge of the Dutchtown High project, said Monday that everything is on course to be completed by the imposed July 14 deadline. "It's hard to predict exactly what day it will be done, but that's our goal," Colomb said. "It's always a challenge at the end, but everything's on pace. "It's been a really great project. I'm very proud of it," he said. "I haven't seen all of the schools in the state, but this one has to rank way up there. I can't imagine there'd be too many other facilities like this." At the new high school site, some contract workers have been toiling away at the school seven days a week to make sure the facility gets finished in time. Kirk Smith, who works for All-Right Electric, the electricians hired to wire up the new high school, said he's been averaging seven-day work weeks at the site since October of last year. "I've had five days off since January," Smith said. He said a major portion of his work, installing intercoms and fire alarms, isn't completed yet. "If I don't get that done, nobody's going to be going to school," he said, adding that there is enough time to get his portion completed. Another contract worker, Kenny Spiers of Gonzales, who works for Chuckleberry's Commercial Flooring in Baton Rouge, said his crew, too, will have to shift into an even higher gear to finish up by their deadline. "We'll probably have to work weekends and get some more men out here to get done," Spiers said. And principal Conrad Braud said school faculty will be ready to help however they can. "We'll probably be in here at midnight bringing in furniture," he said. Songy said some of the new high school's computers are scheduled to begin arriving this week. Local folks may be able to get a sneak peek at the new, spawling facility if all goes as planned. Braud said he's hoping to host public tours in the days leading up to the new school year. "We have a script all ready for student tour guides," Braud said. Those taking the tour will likely marvel at the sheer size of the facility, with its layout of classes, offices, auditorium, band facilities, resource rooms, science labs and home economics labs - and the expansive second-floor library. "That's the high point, I think, the library," Braud said. The principal said he's especially looking forward to show off the new school to graduates of the old Dutchtown High School. "They've been watching it coming up for three years and they want to see what it looks like inside. And it's pretty spectacular." Over 900 students are expected to fill the halls at Dutchtown High, while Duplessis Primary will be welcoming 700 students into its classrooms come Aug. 12.
|